Machine and process information
Provide the machine manufacturer, model, approximate year, product/process description, required cycle time and the operational problems that are driving the project.
Automation hardware
Photograph PLC CPUs, I/O modules, HMI panels, drives, safety controllers, network switches and important device nameplates. Exact order numbers are more useful than manufacturer names alone.
Software and documentation
Existing PLC/HMI source files, electrical drawings, manuals, parameter backups and network lists can significantly reduce discovery work. State clearly if these are missing.
Required changes
Separate mandatory requirements from desirable improvements: obsolete hardware replacement, new product formats, additional sensors, better diagnostics, remote access, traceability or integration with other equipment.
Shutdown and commissioning constraints
The available production shutdown window strongly affects retrofit strategy. Identify when installation can occur, whether offline testing is possible and what production acceptance criteria must be met.